Case Study

Client:
Highways England

Project type:
Topographical and Underground Utilities Surveys

Location:
North England

Overview

Subscan undertook 3D Topographical and Underground Utilities Surveys in the central reservation along a 4km stretch of highway, along with the excavation of 16 trial trenches to verify the Underground Utilities.

Subscan were appointed to undertake 3D Topographical and Underground Utilities Surveys in the central reservation along a 4km stretch of A66. The Project also included excavations of 16 trial trenches to verify the Underground Utilities identified within the survey as part of the barrier replacement scheme.

As part of the project Subscan deployed 3 teams of 2 surveyors to complete the full works required by the project, within 10 working days of site work. Underground Utility Surveyors located numerous services located along the survey area and were able to trace all of them with great precision.

Topographical surveyors established a rigid control network prior to carrying out a full 3D survey of the area as well as mapping all the Utilities found by the Underground utility Surveyors.

Trial trench excavation teams were able to expose the services found by the Underground Utility Surveyors within the trial trenches, which then verified the accuracy of the survey to the client.

Lead Surveyors produced detailed drawings and reports which were delivered to the client within the time allocated.

Client Testimonial

“The Subscan UDS team of surveyors and drainage engineers helped our minor works team out again and did a thoroughly professional job. We will continue to work with Subscan on LNE projects throughout the region.”

Lee Sanderson, Building & Civils Project Manager, Construction Marine Ltd